To remodel the new building located on Avenida Costera Miguel Aleman, the Secretariat directly assigned a contract for 112 million 078,890 pesos, valid until last year.

The contract established that the building should be delivered on December 31, 2021. According to the report on the physical and financial progress of contracts issued by the General Directorate for the Development of Physical Infrastructure of the Ministry of Health, there was a physical progress of 93.78% on the work till December last year.

Conservation and maintenance work was planned for the auditorium, offices, roofs, terraces and parking lot. They also included electrical, plumbing and air conditioning installations; voice, data, audio and video as well; Fire Fighting, Signage, Finish, Masonry, Carpentry and Blacksmithing.

In addition, according to information obtained through Transparency, the Ministry of Health has invested 136,880 pesos in signs and 585,087 pesos in freight and evacuation for the new headquarters.

Staff

Earlier, in October 2021, Jorge Alcoasar Varela, the health secretary, announced that the transfer had already begun. In the first phase, 100 workers — between Central, Upper and Base Command — will move from four regions: the Office of the Secretary, Under Secretary for Prevention and Health Promotion; Economic Analysis and Administration and Finance Units, as well as the Institute of Health (Insabi).

However, in response to a request for transparency, the SSA said that as of November 2021, only 27 people had left the secretary’s office.